United States ex rel. International Brotherhood of Electrical Workers Local Union No. 98 v. Fairfield Co.

United States District Court, E.D. Pennsylvania

August 26, 2019

UNITED STATES OF AMERICA, ex rel INTERNATIONAL BROTHERHOOD OF ELECTRICAL WORKERS LOCAL UNION NO. 98
v.
THE FARFIELD COMPANY

          MEMORANDUM

          KEARNEY, J.

         Years after restoring a railroad track under a contract with Southeastern Pennsylvania Transit Authority partially funded by the United States, a contractor is now answering claims it did not pay forty-two of its groundmen employees at the prevailing wage required by the Department of Labor for the electrical services they provided well over a decade ago. An electricians' union filed this False Claims Act claim alleging the contractor submitted false certified payrolls and certificates of compliance to the municipal authority by having its groundmen employees-who are neither classified as nor paid by the contractor as journeymen electricians-perform journeyman electrical work beyond simply assisting the journeymen. Before proceeding to a bench trial, the contractor seeks summary judgment arguing the union's misclassification, liability and damages theories are disproved by its own witnesses, some of its claims are barred by the statute of limitations and, in any case, the contractor did not submit a record or statement for payment by the federal government and it did not knowingly submit a false claim. Genuine issues of material fact regarding the work groundmen performed individually preclude summary judgment. But we now write to principally address the ability to challenge claims made to a municipal authority before Congress amended the False Claims Act to allow recovery for these claims.

         I. Undisputed facts material to summary judgment.[1]

         The Farfield Company is a construction contractor.[2] In 2001, Farfield contracted with the Southeastern Pennsylvania Transportation Authority ("SEPTA")[3] for work on five federally funded projects improving Philadelphia-area transit systems, including under a March 15, 2002 contract between Farfield and SEPTA for the Wayne Junction to Glenside Project ("Wayne Junction Project" or "Project").[4] Through the Project, SEPTA sought to improve a seven-and-a-half mile stretch of railroad track between Wayne Junction and the Glenside train station.[5]

         As required by the Davis-Bacon Act, [6] the contract between Farfield and SEPTA provided in relevant part:

• "[a]ll laborers and mechanics employed or working upon the site of the work ... will be paid unconditionally ..., the full amount of wages and bonafide [sic] fringe benefits (or cash equivalents thereof) due at time of payment computed at rates not less than those contained in the wage determination of the Secretary of Labor which is attached hereto and made part hereof, regardless of any contractual relationship which may be alleged to exist between the Contractor and such laborers and mechanics."
• "[s]uch laborers and mechanics shall be paid the appropriate wage rate and fringe benefits on the wage determination for the classification of work actually performed, without regard to skill, ...."
• "[l]aborers or mechanics performing work in more than one classification may be compensated at the rate specified for each classification for the time actually worked therein: provided, that the employer's payroll records accurately set forth the time spent in each classification in which work is performed."[7]

         At some point after Farfield began working on the Wayne Junction Project in 2002, the International Brotherhood of Electrical Workers Local Union No. 98 "engaged in an investigation concerning Farfield's practices"[8] allegedly undercovering a scheme of under-bidding prevailing wage projects by classifying workers at lower hourly wages in violation of the Davis-Bacon Act.[9] Local 98 alleges Farfield had its groundmen perform skilled electrician work but paid them at a lower, unskilled work rate rather than the rate for skilled electrical work.

         The parties cite many worker classifications: groundman, laborer, lineman, journeyman lineman, journeyman indoor wireman, journeyman outdoor lineman, foreman indoor wireman, apprentice indoor wireman, and journeyman electrician. The parties do not clearly explain the differences between the dizzying array of positions. Notwithstanding the various classifications, Local 98 conceded at oral argument we may divide workers into two buckets: groundmen and laborers in one bucket and linemen, journeymen, foremen, wiremen, and apprentices in the other bucket. It appears the distinction is based on experience in the electrical field.

         In September 2004, two years into Farfield's work on the Project, the United States Department of Labor audited Farfield's classification of its workers.[10] There is no dispute the Department of Labor found four carpenters should have been paid at a higher prevailing rate on the Project totaling $811.52 which Farfield paid.[11] Farfield contends the Department of Labor found no violation of its classification of employees as laborers, groundmen, linemen, and electricians, citing a 2012 affidavit of John Kleimo, Farfield's Vice President and Secretary.[12]Local 98 disputes this, arguing "[t]he record does not contain any admissible evidence indicating" the Department of Labor's finding and "there is no admissible record evidence addressing the scope, extent or focus of the DOL's investigation."[13]

         Almost ten years ago, Local 98 filed a sealed qui tam complaint alleging Farfield's scheme to intentionally pay its workers wages lower than required by the Davis-Bacon Act and then submit claims to the federal government for payment based on certifications it complied with the Davis-Bacon Act violated the False Claims Act, 31 U.S.C. § 3729 et seq.

         Two years later, the United States declined to intervene in the action. The court unsealed the complaint. Local 98 filed an amended complaint on February 3, 2012.[14] In its amended complaint, Local 98 again alleged Farfield intentionally and knowingly misclassified workers performing electrician's work to gain a competitive bidding advantage on the same federally funded construction projects between 2001 and 2009.[15] Local 98 alleges Farfield submitted fraudulent certified payroll records intending those documents to be material in the federal government's decision to pay the false claims violating the False Claims Act, 31 U.S.C. § 3729(a)(1)(B).[16]

         After motion practice and years of discovery including the appointment of a special discovery master to handle discovery disputes, the Clerk of Court assigned this matter to us in late September 2018. We directed a second round of motion practice on the issue of the Department of Labor's jurisdiction under the primary jurisdiction doctrine and, after finding we could proceed to resolve this case, we issued a scheduling order setting the parties' pre-trial obligations and a trial date.[17]

         II. Analysis.

         Farfield now moves for summary judgment arguing: (1) Local 98's own witnesses and evidence disprove their misclassification, liability and damages theories; (2) Farfield submitted its bills to SEPTA, not the United States Government as required by the False Claims Act at the relevant time before 2008; (3) Farfield did not knowingly submit a false claim; and (4) some of Local 98's claims are barred by the applicable statute of limitations.[18]

         Local 98 responds (1) the record shows Farfield falsely certified compliance with the Davis-Bacon Act; (2) the amended False Claims Act applies to bills submitted to SEPTA; (3) Farfield's reliance on the Department of Labor's 2004 audit is not relevant to its state of mind and the question of whether it knowingly submitted a false claim is a question for trial; and, (4) the statute of limitations does not bar its claims.

         A. The Davis-Bacon Act applies under the False Claims Act.

         The wage rate requirements of the Davis Bacon Act apply to "every contract in excess of $2, 000, to which the Federal Government or the District of Columbia is a party, for construction, alteration, or repair, including painting and decorating, of public buildings and public works of the Government or the District of Columbia that are located in a State or the District of Columbia and which requires or involves the employment of mechanics or laborers ....[19] Every such contract "shall contain a provision stating the minimum wages to be paid various classes of laborers and mechanics" and "minimum wages shall be based on the wages the Secretary of Labor determines to be prevailing for the corresponding classes of laborer and mechanics employed on projects of a character similar to the contract work in the civil subdivision of the State in which the work is to be performed ... ."[20]

         A claim under the False Claims Act may be predicated on an alleged violation of the Davis-Bacon Act.[21] Local 98 alleges Farfield misclassified its groundmen workers in violation of the Davis-Bacon Act and then submitted fraudulent certified payrolls for payment by the federal government under the False Claims Act, 31 U.S.C. § 3729(a)(1)(B), making "any person who -knowingly makes, uses, or causes to be made or used, a false record or statement material to a false or fraudulent claim ... liable to the United States Government for a civil penalty ... plus 3 times the amount of damages which the Government sustains because of the act of that person."[22]

         B. The False Claims Act applies even though Farfield performed work under a contract with SEPTA.

         We begin with a potentially dispositive question of law. Farfield argues it is entitled to summary judgment because it submitted bills for payment to SEPTA which is not the federal government. Farfield argues it did not submit "a false record or statement to get a false or fraudulent claim paid or approved by the Government" as required by the language of the False Claims Act before its amendment in 2009. We are persuaded by recent authority to apply the False Claims Act as amended in 2009.

         Before May 2009, section 3729(a)(1) and (2) of the False Claims Act imposed liability on "any person who ... (1) knowingly presents, or causes to be presented, to an officer or employee of the United States Government or a member of the Armed Forces of the United States a false or fraudulent claim for payment or approval;" or "(2) knowingly makes, uses, or causes to be made or used, a false record or statement to get a false or fraudulent claim paid or approved by the Government."[23]

         To resolve a split in the circuit courts, the Supreme Court granted certiorari to resolve the proper interpretation of section 3729(a) of the False Claims Act and, in its June 9, 2008 Allison Engine decision, held a defendant must make a false record or statement "to get" a false or fraudulent claim "paid or approved by the Government."[24] The Court held "a defendant must intend that the Government itself pay the claim"; and "is not the same as getting it paid using 'government funds.'"[25] The Court reasoned "eliminating this element of intent... would expand the FCA well beyond its intended role of combating 'fraud against the Government.'"[26]

         In response to Allison Engine, Congress enacted the Fraud Enforcement Recovery Act of 2009 ("FERA")[27] amending, inter alia, section 3729 of the False Claims Act. FERA struck language from the False Claims Act requiring presentation "to an officer or employee of the United States Government or a member of the Armed Forces of the United States" and the language "to get a false or fraudulent claim paid or approved by the Government." As amended by FERA, the False Claims Act now reads, inter alia, "any person who - (A) knowingly presents, or causes to be present, a false or fraudulent claim for payment or approval; [or] (B) knowingly makes, uses, or causes to be made or used, a false record or statement material to a false or fraudulent claim; ... is liable to the United States Government for a civil penalty of not less than $5, 000 and not more than $10, 000 ... plus 3 time the amount of damages which the Government sustains because of the act of that person."[28]

         Congress made FERA effective "as if enacted on June 7, 2008"-two days before the Supreme Court's Allison Engine decision-and applicable "to all claims under the False Claims Act (31 U.S.C. 3729 et seq.) that are pending on or after that date; , .."[29] Importantly, when referring to the retroactivity of section 3731(b), Congress applied it "to cases pending on the date of enactment."[30]

         The question today is which version of the False Claims Act applies to Local 98's claim; the pre-FERA version or the post-FERA version? The answer turns on the interpretation of the word "claims." There is no dispute SEPTA made its final payment to Farfield on December 6, 2007, well before the effective date of FERA, for work on the Wayne Junction Project.[31] And there is no dispute Local 98 filed its original complaint on September 17, 2009, three months after the effective date of FERA.

         Farfield argues FERA does not apply here and it has no liability under the pre-FERA version of the False Claims Act. To be liable under the pre-FERA version of the False Claims Act, claims must be presented to the federal government for payment and, as Farfield argues, SEPTA is not the federal government, and the use of federal funds on the Project is not sufficient for pre-FERA False Claims Act liability. To support its argument, Farfield points to section 3729 defining a "claim" as "any request or demand, whether under a contract or otherwise, for money or property ...."[32] So, argues Farfield, when Congress made FERA effective June 7, 2008 and made it applicable to "all claims under the False Claims Act ... that are pending on or after that date," Congress meant "claim" to mean a request or demand for money. Congress did not intend the word "claim" to mean a lawsuit or "case" and we must assume Congress would have written the words "all cases under the False Claims Act... that are pending on or after" June 7, 2008 if it so intended.

         When addressing Farfield's 2013 motion to dismiss arguing applying FERA violates the Ex Post Facto Clause of the Constitution, Judge Stengel held FERA's amendments to section 3729(a)(2) applied to all pending cases arising under the False Claims Act pending on or after June 7, 2008.[33] Farfield again challenges FERA's application, but not under the Ex Post Facto Clause. It instead argues the term "claim" means a demand for money, not a case or lawsuit.

         Although our Court of Appeals has not determined this issue, Farfield cites three cases within this Circuit interpreting "claims" as demands for money, not cases under the False Claims Act: a 2010 decision from the United States District Court for the District of New Jersey;[34] a 2010 decision from the United States District Court for the Western District of Pennsylvania;[35] and a 2012 decision from this district.[36]

         We are persuaded by the more recent expansive reasoning of the United States Court of Appeals for the Sixth[37] and Seventh Circuits[38] holding the word "claim" in FERA's section 4(f)(1) refers to a civil action or case pending on or after June 7, 2008. The cases cited by Farfield from within this district were decided before Garbe and the third, Spay, does not address Sanders.

         In Sanders, the United States Court of Appeals for the Sixth Circuit considered the language of FERA applying the rules of statutory construction; Congress's intent evidenced by the statute's language; and the Senate Report accompanying FERA and particularly its reference to '"FCA cases" and two instances where the Senate Report uses the term "claim" to mean an FCA case creating inconsistent terminology weakening the import of the Senate Report. The Sixth Circuit recognized "the strongest argument in favor of reading 'claims' in § 4(f)(1) [of FERA] to mean a demand for payment is the structure of FERA itself and Congress's use of the word "cases" in nearby section § 4(f)(2).[39] Nevertheless, the Sixth Circuit concluded "using the technical definition in context ('claims under the False Claims Act') provides a strained reading, and therefore it is not appropriate to import the statutory definition of 'claim'-which applies for purposes of § 3729-into § 4(f). The fact that the two parts of § 4(f)'s exceptions to the effective date of FERA's amendments to the FCA were not drafted simultaneously reduces the strength of the structural argument. The use of 'claims' elsewhere in the statute when the clear meaning is 'cases' buttresses our conclusion. Consulting precedent and legislative history failed to further illuminate our analysis."[40]

         The United States Court of Appeals for the Seventh Circuit in Garbe reached the same conclusion. In Garbe, defendant contractor argued the pre-FERA statute covered only requests for reimbursements pending on or after June 7, 2008, not relator's case. The Court of Appeals, relying on its earlier decisions, the Sanders decision from the United States Court of Appeals for the Sixth Circuit as well as decisions from the United States Courts of Appeals for the Second and Fifth Circuits, held "claims" in FERA's section 4(f)(1) means "case" not individual requests for payments.[41] The court in Garbe reasoned this "interpretation ... best reflects the text and structure of the statute" and it "makes no sense" to construe "claims" to mean "requests for payment."[42]The court explained "[t]here is no such thing as a request or demand for payment under the False Claims Act" and construing FERA as retroactive only for requests for payment "is also in tension with Congress's state goal of changing Allison Engine's interpretation of § 3729(a)" because Congress made FERA retroactive to two days before Allison Engine to "eliminate the approach taken in Allison Engine without reopening judgments that were already final when Allison Engine was decided."[43] The court rejected the contractor's argument the False Claims Act's definition of "claim"- "any request or demand ... for money"-should control, explaining Congress's "free use of 'claim' (along with 'action') to mean 'civil action' throughout the FCA further support the argument that § 4(f)(1) was not meant to incorporate the definition in § 3729(b)(2)(A)."[44]

         Persuaded by the reasoning of Sanders and Garbe, we conclude the False Claims Act as amended by FERA applies to Local 98's case and deny summary judgment on this ground.

         C. The statute of limitations does not bar Local 98's claims.

         Farfield seeks summary judgment on part of Local 98's claims as barred by the statute of limitations in the False Claims Act. Section 3731(b) of the False Claims Act provides "[a] civil action under section 3730 may not be brought - (1) more than 6 years after the date on which the violation of section 3729 is committed, or (2) more than 3 years after the date when facts material to the right of action are known or reasonably should have been known by the official of the United States charged with responsibility to act in ...


Buy This Entire Record For $7.95

Download the entire decision to receive the complete text, official citation,
docket number, dissents and concurrences, and footnotes for this case.

Learn more about what you receive with purchase of this case.