BOHRER-REAGAN CORP. v. MODINE MFG. CO.

June 20, 1977

BOHRER-REAGAN CORPORATION
v.
MODINE MANUFACTURING COMPANY



The opinion of the court was delivered by: TROUTMAN

 TROUTMAN, J.

 Plaintiff, a Pennsylvania corporation, is suing to recover for damages allegedly resulting from the malfunction of six heating and ventilating units which plaintiff claims were purchased from defendant, a Wisconsin corporation. The goods in question were purchased from Schemenauer Manufacturing Company (Schemenauer), an Ohio corporation, through an order which was placed at Schemenauer's Villanova, Pennsylvania, office. Since the purchase, all of Schemenauer's outstanding stock was acquired by defendant and Schemenauer became a wholly-owned subsidiary of defendant. Furthermore, Schemenauer underwent a corporate name change and became Modine Manufacturing Company, an Ohio corporation (Modine-Ohio).

 Defendant also contends that it is not a proper party to the suit. The contract was with Schemenauer, who has since become Modine-Ohio, a wholly-owned subsidiary with a separate identity. Modine-Ohio is thus the proper party to this action.

 Plaintiff counters by arguing that defendant was engaged with plaintiff in a series of communications and transactions regarding the performance of the goods which led plaintiff to believe it was dealing with a Wisconsin corporation. Thus, the "Corporate Veil" should be pierced and defendant, not Modine-Ohio, should be the party in this action. Furthermore, since a Wisconsin defendant is properly in this action, the Wisconsin statute of limitations, which allows a six-year period for bringing such actions, is the applicable law in this action.

 In diversity actions Federal courts must apply the conflict of law rules of the states in which they sit. Klaxon Company v. Stentor Electric Manufacturing Company, 313 U.S. 487, 85 L. Ed. 1477, 61 S. Ct. 1020 (1941), Day & Zimmermann, Inc. v. Hawley K. Challoner, 423 U.S. 3, 46 L. Ed. 2d 3, 96 S. Ct. 167 (1975). Pennsylvania courts apply the law of the place where a contract is made and where it is to be performed. See Craftmark Homes, Inc. v. Nanticoke Construction Co., 526 F.2d 790, 792 (3d Cir. 1975), footnote 2, and the cases cited therein.

 In the instant case, it is not clear whether the contract was formed in Pennsylvania or Ohio. The order for the goods was placed with Schemenauer's office in Pennsylvania, but the goods were manufactured in Ohio and shipped into Pennsylvania. It is not clear whether the contract could be accepted in Pennsylvania and made binding upon Schemenauer or whether all orders had to be forwarded to Ohio to be accepted. This is not a deciding issue, however, for it is the law of Pennsylvania that if the place of contract formation differs from the place of performance, the law of the place of performance governs. Robert H. Fox Co. v. Keystone Driller Company, 232 F.2d 831, 832 (3d Cir. 1956); York Metal & Alloys Co. v. Cyclops Steel Co., 280 Pa. 585, 588, 124 A. 752 (1924). Here, the goods were to be installed in Pennsylvania and allegedly were to perform without damage from leakage in Pennsylvania. Thus, Pennsylvania is the place of performance and Pennsylvania's statute of limitations applies.

 The cases cited by plaintiff are wholly inapposite. They are Wisconsin cases applying Wisconsin choice-of-law rules. Such an application is inappropriate for this Court for the reasons cited in the Klaxon and Day & Zimmerman cases.

 Therefore, we conclude as a matter of law, that the Pennsylvania statutory period of four years applies in this case. This finding is not dependent in any way upon the relationship of the defendant and the Modine Manufacturing Company in Ohio, so we need not determine whether or not the "Corporate Veil" can be pierced.

 ORDER

 TROUTMAN, J.

 AND NOW, this 20th day of June, 1977, IT IS ORDERED that defendant's motion for ...


Buy This Entire Record For $7.95

Download the entire decision to receive the complete text, official citation,
docket number, dissents and concurrences, and footnotes for this case.

Learn more about what you receive with purchase of this case.