Searching over 5,500,000 cases.


searching
Buy This Entire Record For $7.95

Download the entire decision to receive the complete text, official citation,
docket number, dissents and concurrences, and footnotes for this case.

Learn more about what you receive with purchase of this case.

MAR RAY v. FRANK SCHROEDER ET AL. (09/27/76)

decided: September 27, 1976.

MAR RAY, INC., A PENNSYLVANIA CORPORATION, APPELLANT,
v.
FRANK SCHROEDER ET AL.



COUNSEL

Anthony J. Martin, Monroeville, for appellant.

Edward C. Leckey, Pittsburgh, for appellee.

Watkins, President Judge, and Hoffman, Cercone, Price Van der Voort, and Spaeth, JJ.

Author: Price

[ 242 Pa. Super. Page 15]

On December 23, 1974, the lower court sustained appellee's preliminary objections to a mechanic's lien claim filed by appellant Mar Ray, Inc. We reverse.

The documentary evidence in the record reveals that on August 1, 1968, appellant contracted with Arkay Construction Company, Inc. (Arkay), to perform carpentry work on property located in Allegheny County, Pennsylvania, known as Village in the Park. Village in the Park was owned by appellees Frank Schroeder, Barbara McCormick, and Warren H. Van Kirk, trading as Shadyside Investment Company, and was leased by appellees Albert B. Starr and William K. Kershbaumer. The contract designated Arkay as the "Contractor" and appellant as the "Subcontractor." The contract price was $235,000.00. Appellant's lien claim is for the sum of $65,192.51.

[ 242 Pa. Super. Page 16]

The contract, a copy of which is attached to appellant's lien claim, contains a waiver of the right to file a lien claim,*fn1 and based on the contractual waiver, the lower court sustained appellees' preliminary objections to the claim.*fn2

Appellant's claim avers that the lien was not filed pursuant to the contract containing the waiver, but to another contract. According to appellant's claim, on or about June 15, 1969, Arkay was no longer able to perform its obligations under the contract with the owners. As a result of this failure, appellee Albert Starr agreed to pay appellant all past sums due and owing to appellant, in consideration for appellant's promise to complete the carpentry work at Village in the Park. The claim further avers that the work was completed on July 29, 1969. Appellant contends that the second contract did not contain a waiver of liens and that the mechanic's lien was filed pursuant to that contract.

It is unclear whether appellees contend that the lien claim was filed pursuant to the first contract, or whether appellees contend that the waiver in the first contract precludes appellant from filing a lien claim under the second contract. The lower court apparently accepted the first of these contentions, for the lower court's opinion contains no mention of the alleged second contract.

[ 242 Pa. Super. Page 17]

Indeed, there is nothing in the record, other than the assertion in appellant's claim, to indicate the existence of a second contract.

If the lien claim was filed pursuant to a second contract which contained no waiver, it appears that appellant would be entitled to file the lien claim. N. Green & Co. v. Thompson, 172 Pa. 609, 33 A. 702 (1896). The lower court, however, by sustaining the appellees' preliminary objections, has denied the appellant an opportunity to prove the existence of the second contract. The lower court apparently assumed either that the lien claim was filed pursuant to the first contract; or that the waiver in the first contract precluded filing of a lien claim under the second; or that the second contract never existed. None of these assumptions is warranted on the ...


Buy This Entire Record For $7.95

Download the entire decision to receive the complete text, official citation,
docket number, dissents and concurrences, and footnotes for this case.

Learn more about what you receive with purchase of this case.