Searching over 5,500,000 cases.


searching
Buy This Entire Record For $7.95

Download the entire decision to receive the complete text, official citation,
docket number, dissents and concurrences, and footnotes for this case.

Learn more about what you receive with purchase of this case.

GREENTREE BOROUGH v. TORTORETE (06/17/65)

decided: June 17, 1965.

GREENTREE BOROUGH, TO USE, APPELLANT,
v.
TORTORETE



Appeal from order of Court of Common Pleas of Allegheny County, April T., 1962, No. 401, in case of Borough of Greentree, to use of Castelli Construction Company, Inc., v. John N. Tortorete et al.

COUNSEL

Charles Kirshner, with him Rosenberg and Kirshner, for appellant.

Stephen A. Zappala, with him Zappala & Zappala, for appellees.

Ervin, P. J., Wright, Watkins, Jacobs, and Hoffman, JJ. (Montgomery and Flood, JJ., absent). Opinion by Jacobs, J.

Author: Jacobs

[ 205 Pa. Super. Page 533]

The sole issue in this appeal is whether or not the lower court abused its discretion in granting a new trial.

Plaintiff, Castelli Construction Company, Inc., sued on an oral contract under which it had agreed to supply labor and material for defendant, John Tortorete, who was awarded a contract by the Borough of Greentree to perform certain construction work. Defendant, Continental Casualty Company, was surety on Tortorete's labor and material payment bond on the Greentree contract. Under the oral contract Tortorete would receive 9 1/2 % of the total contract price and plaintiff, after payment of all labor and material, would receive the balance. After about 12 weeks of work under the contract, plaintiff was told by Tortorete to stop work. It was disputed at trial whether this termination was

[ 205 Pa. Super. Page 534]

    due to plaintiff's slowness which jeopardized completion by the contract date, or pursuant to an oral agreement that Tortorete could take over the job completely at any time he desired.

Plaintiff sued for $9,118.56, the price of the material supplied and labor performed, plus interest. The jury awarded plaintiff $7,511.00, which included interest, against both defendants. The lower court awarded a new trial, finding error in the following instruction contained in the charge:

"If Castelli breached this contract and you believe Tortorete was justified in discharging him, Castelli would be entitled to be reasonably compensated for all the work done and materials furnished up to August 4, 1961, if you believe he was justified. That's up to you to make that finding first. If Tortorete was not justified in discharging him and he had not breached this oral contract, if the caliber of work done and the time in which it was done were satisfactory, then Castelli Construction Company is entitled to ninety and a half per cent of the total contract price $37,500.00, less the amount he must pay Tortorete for all the bills for materials paid for and furnished by Tortorete, which amounts to about $8,683.00, plus 17 per cent interest."

From the order granting a new trial, plaintiff appeals.

It is a well settled rule that we will not reverse the lower court's grant of a new trial unless there is clear abuse of discretion or error of law. Edelson v. Ochroch, 380 Pa. 426, and cases cited therein. We find no abuse of ...


Buy This Entire Record For $7.95

Download the entire decision to receive the complete text, official citation,
docket number, dissents and concurrences, and footnotes for this case.

Learn more about what you receive with purchase of this case.