CHESTER MUNICIPAL AUTHORITY v. DELP. (11/18/52)

November 18, 1952

CHESTER MUNICIPAL AUTHORITY, APPELLANT,
v.
DELP.



Appeal, No. 16, Jan. T., 1953, from order of Court of Common Pleas of Chester County, July T., 1951, No. 66, in case of Chester Municipal Authority v. F. Vernon Delp, Virginia H. Delp, Ernest M. Delp and Mildred E. Delp. Order affirmed.

COUNSEL

Clement J. McGovern, with him William J. Scarlett and J. H. Ward Hinkson, for appellant.

J. Paul MacElree, with him Lawrence E. MacElree, for appellees.

Before Drew, C.j., Stern, Stearne, Jones, Bell, Chidsey and Musmanno, JJ.

Author: Chidsey

[ 371 Pa. Page 601]

OPINION BY MR. JUSTICE CHIDSEY

Appellant, Chester Municipal Authority, instituted an eminent domain proceeding. The Authority is the owner of a water system in Chester and vicinity. It desired to construct an underground water pipe-line. By resolution on April 6, 1950 the Authority acquired and appropriated "... such rights of way or easements

[ 371 Pa. Page 602]

    on and under the lands hereinafter described as are necessary to construct, operate and maintain said water pipe-line and its accessories, in the said locations and routes along, about, and under the line shown as the center line of said rights of way or easements on the said blueprint plans by Francis S. Friel, engineer, together with rights of entry thereto, along, about and upon said line, for construction, maintenance or renewal thereof." Apparently, the Authority started work on appellant's land on June 3, 1950 and completed the work about July 31, 1950.

On September 11, 1950 a jury of view was appointed which viewed the premises on October 10, 1950.On January 4, 1951 the Authority passed the following supplemental resolution: "WHEREAS, the Authority desires hereby to define and limit the extent and character of the rights of way acquired under and by virtue of the said Right of Way Resolutions: NOW, THEREFORE, it is hereby resolved by the Board of Chester Municipal Authority -- 1. That all rights of way or easements heretofore appropriated by the Authority for the construction, operation, maintenance and ultimate renewal of its underground water transmission pipe-line are expressly defined and limited as follows: (a) To the permanent occupation and use of such area underground as shall be required for the installation, construction, joinder, anchorage and support of a single line of prestressed steel and concrete water-main pipe, of diameters varying from 48 inches to 30 inches, as well as for the accommodation of access manholes, valves, boxes, conduits and other accessories -- all as shown for each individual property upon the blue-print plan attached to the bond tendered to the owner of such property in the condemnation proceedings instituted following the adoption of the aforementioned Right of Way Resolutions; and (b) To the

[ 371 Pa. Page 603]

    permanent occupation and use of such surface area as shall be required for the said manholes, valves, boxes and other accessories, including markers; and (c) To the temporary occupation and use of such surface area as shall be reasonably required in and about the original construction of the said pipe-line -- said area, however, not to exceed 20 feet in width to either side of the center of said pipe-line, to be entered upon and reached only along the line of the said pipe-line right of way and not across other lands of the owners; and (d) To the temporary occupation and use of such surface area as shall at any time or times in the future be reasonably required for the operation, maintenance or renewal of said pipe-line and/or accessories -- said area, however, not to exceed 10 feet in width to either side of the center of said pipe-line, to be entered upon and reached only along the line of the said pipe-line right of way -- the Authority to be and remain responsible for any and all damage to buildings, fences, crops, trees, or other property occasioned by reason of any such future occupation and use, if and when such damage be sustained. 2. That this resolution constitutes a supplement to the aforementioned Right of Way Resolutions of April 6, 1950, and May 4, 1950, respectively; and the terms and provisions hereof are intended to limit the rights of the Authority acquired thereunder and to define the responsibility of the Authority in connection with the exercise of such rights. 3. That all resolutions, motions, or parts thereof, that may be inconsistent herewith are hereby repealed. 4. That the effective date hereof shall, as to each property involved, be the date of its original appropriation by Resolution of this Board."

In May, 1951, the viewers met and awarded $5,920.96. The appellant took exceptions to the report of the viewers and ...


Buy This Entire Record For $7.95

Download the entire decision to receive the complete text, official citation,
docket number, dissents and concurrences, and footnotes for this case.

Learn more about what you receive with purchase of this case.