AGGER v. FRANK DONATELLI & CO. (10/01/52)

October 1, 1952

AGGER
v.
FRANK DONATELLI & CO., INC.



COUNSEL

Zeno Fritz, Pittsburgh, for appellant.

Harry S. Kalson, Pittsburgh, for appellee.

Before Rhodes, P. J., and Hirt, Reno, Dithrich, Ross, Arnold and Gunther, JJ.

Author: Arnold

[ 171 Pa. Super. Page 632]

ARNOLD, Judge.

According to the complaint, this action of assumpsit was upon a contract, partly oral and partly written. The jury found for the plaintiff and defendant appealed.

The testimony shows that the defendant contended there was no contract but merely proposals and counter-proposals.

The evidence would sustain jury findings that sometime in June, 1947, negotiations began between the parties for the plaintiff to manufacture an iron railing, to be erected on a job which the defendant was performing for the State Highway Department. Plaintiff was shown plans and specifications which called for galvanized fittings. In July of 1947 defendant asked plaintiff to bid for the manufacture of the railing in accordance with 'sketch approved by the State Highway Department.' This sketch did not indicate the type of material. Plaintiff wrote the defendant offering to furnish and erect a railing for a certain price, but stating that 'since the railing is to be welded we

[ 171 Pa. Super. Page 633]

    have figured on using black steel pipe.' The welding prevented the use of galvanized fittings, but plaintiff contended that an employe of the defendant approved the use of black steel pipe and welding. Defendant denied the authority of its employe so to approve, and also denied that any approval had been given.

Plaintiff wrote defendant that it was proceeding to construct the railing and was making certain changes, but would 'submit a sample of both of these pieces to them [the engineers for the Highway Department] for approval.' Plaintiff's testimony that they were so approved was denied by the defendant. Upon its delivery at the job the railing was rejected by the Highway Department because the fittings were not galvanized. Thus it could not be used and the defendant had to obtain the proper railing elsewhere.

The court charged that 'there is no question that a contract did exist, because the parties agree that a contract existed * * *.' This was objected and excepted to by the defendant and the court refused to correct the charge, simply stating that the only question was whether or not the contract had been performed according to the terms.

Since defendant's testimony denied any contract, and since the summary which we have set forth, if believed by the jury, showed that there was no contract, this was in error and a new trial will be granted. The alleged contract was partly oral and partly written. The credibility of the witnesses was for the jury, and it was not bound to accept the plaintiff's oral testimony even though uncontradicted. Kostello v. Kostello, 159 Pa. Super. 194, 196, 48 A.2d 25; Schwoerer v. Philadelphia, 167 Pa. Super. 356, 359, 74 A.2d 755. If the testimony ...


Buy This Entire Record For $7.95

Download the entire decision to receive the complete text, official citation,
docket number, dissents and concurrences, and footnotes for this case.

Learn more about what you receive with purchase of this case.