United States v. Le Roy Dyal Co.

decided: December 28, 1950.

UNITED STATES
v.
LE ROY DYAL CO., INC.



Author: Goodrich

Before BIGGS, Chief Judge, and GOODRICH and KALODNER, Circuit Judges.

GOODRICH, Circuit Judge.

This appeal concerns the application of a provision for liquidated damages in a contract between the United States, through Commodity Credit Corporation, and LeRoy Dyal Company, Inc., a dealer in potatoes.

Neither side criticizes the findings of fact by the learned District Court. The only issue presented is one of law, but a brief statement of the facts will add to the understanding of the legal question. The contract between the Commodity Credit Corporation and the defendant was made on July 15, 1947. Defendant agreed to operate as a dealer to carry out the 1947 crop Irish potato price support program. The contract provided that the defendant was to purchase potatoes only from eligible growers. Defendant purchased 367,400 pounds of Irish potatoes from a farmer who was not an eligible grower. The defendant did not, at the time of purchase, know that this farmer was not an eligible grower, but that information was readily available to him. The defendant had had business dealings with the Commodity Credit Corporation prior to this contract. The contract provided for payment of $3.00 per hundredweight as liquidated damages if the dealer contracting with the CCC purchased potatoes from an ineligible grower.*fn1

The learned Trial Judge held, as a conclusion of law, that the provision for liquidated damages "is in the nature of a penalty under the circumstances of this case" and gave the plaintiff judgment for nominal damages only. This appeal followed. The sole question before us is the correctness of refusal by the District Court to award the plaintiff the amount stipulated for in the contract and called liquidated damages. It is hardly necessary to add that the name given to the provision in the contract does not determine whether it is to be treated as liquidated damages or as a penalty.

The first question met is the law by which we are to be guided in deciding the case. Many New Jersey decisions have been cited to us. We think it clear that they do not control. The latest Supreme Court decision involving the validity of a liquidated damage provision in a contract made by a United States agency is Priebe & Sons, Inc. v. United States, 1947, 332 U.S. 407, 68 S. Ct. 123, 126, 92 L. Ed. 32. Mr. Justice Douglas, speaking for the majority, applies to the question concerning a stipulation for liquidated damages "the principles of general contract law." The very vigorous minority, in two dissenting opinions, denies the right of the courts to exercise judicial supervision over the liquidated damage term in a contract inserted by government agencies in pursuance of Congressional authority. But neither majority nor minority so much as hints that state law controls. Indeed, in view of the principle declared by the Court in Clearfield Trust Co. v. United States, 1943, 318 U.S. 363, 63 S. Ct. 573, 87 L. Ed. 838, it seems clear to us that whatever the rule is to be, it is not to be determined by reference to decisions of any particular state.

However, the question is not, we think, of controlling importance here. The general principle with regard to liquidated damages is not difficult to state. In Restatement, Contracts ยง 339 it is worded as follows:

(1) An agreement, made in advance of breach, fixing the damages therefor, is not enforceable as a contract and does not affect the damages recoverable for the breach, unless

(a) the amount so fixed is a reasonable forecast of just compensation for the harm that is caused by the breach, and

(b) the harm that is caused by the breach is one that is incapable or very difficult of accurate estimation.

The New Jersey cases state the principle substantially in accordance with the test quoted.*fn2

The Trial Court found as a fact that there was no proof of actual damage suffered by the plaintiff as a result of defendant's breach of contract. This fact is not controlling. If a provision for liquidated damages is upheld the fact that actual damage did or did not occur or was not proved to have occurred does not prevent the recovery of the stipulated sum. There is some dissent on this point, but the statement just made represents the great weight of decided cases.*fn3

The majority of the Supreme Court in Priebe & Sons, Inc. v. United States, cited above, refused enforcement of one of the provisions for liquidated damages in a contract made by the United States through the Department of Agriculture pursuant to the Lend-Lease Act. That decision binds us and this case is to be decided within the limits set by it. The majority pointed out that the law does not today look with disfavor upon liquidated damages provisions in contracts and cited with approval the Restatement of Contracts quoted above. It also said that such provisions "serve a particularly useful function when damages are uncertain in nature or amount or are unmeasurable, as is the case in many government contracts." It is also pointed out that the provisions are to be judged as of the time of making the contract.

In the Priebe case the party contracting with the government was to deliver dried eggs after a given date as specified. It was also to have the eggs inspected prior to delivery. There was a provision for liquidated damages for failure to deliver when required and also another and different provision for liquidated damages for failure to inspect as stipulated. The majority thought that it was "apparent that the only thing which could possibly injure the Government would be failure to get prompt performance when delivery was due." It had no doubt of the validity of the provision for liquidated damages for failure to deliver, but thought that the failure to inspect on time could not ...


Buy This Entire Record For $7.95

Download the entire decision to receive the complete text, official citation,
docket number, dissents and concurrences, and footnotes for this case.

Learn more about what you receive with purchase of this case.